2010 sale of a 70.000 hl brewery to Westafrika
In July 2010, map has closed the contract about the supply of a complete brewery with an annual capacity of 70,000 hl.
The plant was built in 2003 but never delivered. Our mission includes the completion of the brewery plant by a CO2 recovery plant, as well as the overhaul of the refrigeration system and control technology.
In February 2011 the plant was delivered, it consists of malt treatment, malt and rice mills, 4-vessel brewhouse, brewing water tanks, yeast plant, 4 fermenter, 6 maturation tanks, filtration, 2 BBTs, steamboiler, compressed air supply, cooling system, CO2 recovery and flash pasteurization; electrical and control system.
Installation and commissioning of the entire system we are introducing by August 2011.
CIMG2003_200
Short visit on site in June 2011 to see the progress of civil works for starting the installation works.Technical clarification and consultancy.
In August ´11 we started the installation works.
2010 EKU Kulmbach - Germany - disassembling of malt treatment and brewhouse
End of 2009 map received a contract for the dismantling of a 600 hl brewhouse with parts of the malt silo and grinding plants in Kulmbach. We were able to complete the work in February 2010. Currently, investment in Nigeria is re-assembled together with 2 filters, we have also removed, converted to a malt extract production line.
Kontakt
m.a.p. GmbH
modernisation
automation
project-management
Dismantlement and Re-Installation
of brewery machinery and equipment
and malting plants.
Office address:
Flurstrasse 38
85402 Kranzberg
Deutschland
contact person:
Mr. Joachim Rüsse
phone: +49-(0)81 66 - 684052
cell phone: +49-(0)171 - 93 04 678
E-Mail: This email address is being protected from spambots. You need JavaScript enabled to view it.